Project Start Date: 12/3/00 12:01 AM
Project Finish Date: 12/18/00 3:00 PM
| ID | Task_Name | Duration | Start_Date | Finish_Date | Predecessors | Resource_Names |
|---|---|---|---|---|---|---|
| 1 | Release L14 - Release Schedule | 46.87 days? | 12/3/00 12:01 AM | 12/18/00 3:00 PM | ||
| 2 | Release L14 Certification | 0 days | 12/12/00 12:01 AM | 12/12/00 12:01 AM | Everyone | |
| 3 | Pre-push tasks | 44.76 days | 12/3/00 12:01 AM | 12/17/00 10:05 PM | ||
| 4 | DBAs | 17.76 days | 12/12/00 12:01 AM | 12/17/00 10:05 PM | ||
| 5 | Write audit scripts for release | 3 days | 12/12/00 12:01 AM | 12/13/00 4:01 AM | 2 | Ramesh |
| 6 | Export Skinner tables from tsp@stage | 30 mins | 12/15/00 10:05 PM | 12/15/00 10:35 PM | 48FS-6 days | Vishal |
| 7 | Export Resource tables from tsp@stage | 30 mins | 12/15/00 10:35 PM | 12/15/00 11:05 PM | 6 | Vishal |
| 8 | Move the Skinner and Resource .dmp files to PROD | 30 mins | 12/15/00 11:05 PM | 12/15/00 11:35 PM | 7 | Vishal |
| 9 | Verify scripts installed on db1 are correct | 30 mins | 12/15/00 11:35 PM | 12/16/00 12:05 AM | 8 | Vishal |
| 10 | Accelerate hot backup at 8:00 and comment out cron entry for hot backup | 5 mins | 12/16/00 12:05 AM | 12/16/00 12:10 AM | 9 | Ramesh |
| 11 | Run audit scripts against PROD for baseline information | 30 mins | 12/16/00 12:10 AM | 12/16/00 12:40 AM | 10 | Ramesh |
| 12 | Add tablespaces to PROD for L14 | 2 hrs | 12/12/00 12:01 AM | 12/12/00 2:01 AM | 2 | Vishal |
| 13 | Run snapshots 1 hour before release | 30 mins | 12/17/00 9:05 PM | 12/17/00 9:35 PM | 48FS-1 hr | Vishal |
| 14 | Export tsp_environment | 30 mins | 12/17/00 9:35 PM | 12/17/00 10:05 PM | 13 | Vishal |
| 15 | ||||||
| 16 | Sys Admins | 0.03 days | 12/3/00 12:01 AM | 12/3/00 12:16 AM | ||
| 17 | Rollout app servers for Portal | 0 days | 12/3/00 12:01 AM | 12/3/00 12:01 AM | Dan | |
| 18 | Rollout db servers for Portal | 0 days | 12/3/00 12:01 AM | 12/3/00 12:01 AM | Dan | |
| 19 | Rollout Alteon ACE Director for Portal | 0 days | 12/3/00 12:01 AM | 12/3/00 12:01 AM | Arnold | |
| 20 | Update Redzone messaging for outage window | 15 mins | 12/3/00 12:01 AM | 12/3/00 12:16 AM | Mike L | |
| 21 | ||||||
| 22 | Operations Lead | 0 days | 12/12/00 12:01 AM | 12/12/00 12:01 AM | ||
| 23 | Schedule Final Release Meeting (launch minus 1 day) | 0 days | 12/12/00 12:01 AM | 12/12/00 12:01 AM | 2 | Matt |
| 24 | Setup Conference Call via AT&T | 0 days | 12/12/00 12:01 AM | 12/12/00 12:01 AM | 23 | Matt |
| 25 | ||||||
| 26 | Release Engineering | 0.59 days | 12/12/00 12:01 AM | 12/12/00 4:46 AM | ||
| 27 | Create app server tar ball on stage | 30 mins | 12/12/00 12:01 AM | 12/12/00 12:31 AM | 2 | Keith |
| 28 | Create MEP tar ball on stage | 15 mins | 12/12/00 12:31 AM | 12/12/00 12:46 AM | 27 | Keith |
| 29 | Massage the app server tar ball so that configuration is correct for PROD env | 30 mins | 12/12/00 12:46 AM | 12/12/00 1:16 AM | 28 | Keith |
| 30 | Move the app server tar ball to PROD app and http servers machines and untar | 1 hr | 12/12/00 1:16 AM | 12/12/00 2:16 AM | 29 | Keith |
| 31 | Move the app server tar ball to PROD graph server machines and untar | 15 mins | 12/12/00 2:16 AM | 12/12/00 2:31 AM | 30 | Keith |
| 32 | Move the MEP tar ball to BFS1 | 15 mins | 12/12/00 2:31 AM | 12/12/00 2:46 AM | 31 | Keith |
| 33 | Copy PL/SQL scripts from app codebase to db server | 30 mins | 12/12/00 2:46 AM | 12/12/00 3:16 AM | 32 | Keith |
| 34 | Create L14 migration script tar ball | 1 hr | 12/12/00 3:16 AM | 12/12/00 4:16 AM | 33 | Keith |
| 35 | Move migration script tar ball to PROD and untar | 30 mins | 12/12/00 4:16 AM | 12/12/00 4:46 AM | 34 | Keith |
| 36 | ||||||
| 37 | Pre-release L14 Infranet testing | 7.69 days | 12/12/00 12:01 AM | 12/14/00 1:30 PM | ||
| 38 | Setup 'thrash' instance on db2 | 4 hrs | 12/12/00 12:01 AM | 12/12/00 4:01 AM | 2 | Mahender |
| 39 | App servers configured | 1 hr | 12/12/00 12:01 AM | 12/12/00 1:01 AM | 2,17,18,19 | Mike L |
| 40 | Install L14 code on AS6 and HTTP3 | 4 hrs | 12/12/00 12:01 AM | 12/12/00 4:01 AM | 2 | Keith |
| 41 | Price lists installed | 1 hr | 12/12/00 8:00 AM | 12/12/00 9:00 AM | 2 | Allen |
| 42 | Coldbackup of PORTAL database | 4 hrs | 12/12/00 9:00 AM | 12/12/00 1:00 PM | 41 | Ramesh |
| 43 | Remove AS6 and HTTP3 from the production loop | 30 mins | 12/12/00 1:00 PM | 12/12/00 1:30 PM | 42 | Mike L |
| 44 | Test Dynamo to Portal interfaces | 1 day | 12/12/00 1:30 PM | 12/13/00 1:30 PM | 43 | Luke |
| 45 | Infranet administrator testing | 1 day | 12/13/00 1:30 PM | 12/14/00 1:30 PM | 44 | CS |
| 46 | ||||||
| 47 | Release Tasks | 1.6 days | 12/17/00 10:00 PM | 12/18/00 10:50 AM | ||
| 48 | Conference call starts - final decision point | 5 mins | 12/17/00 10:00 PM | 12/17/00 10:05 PM | Everyone | |
| 49 | Enable Redzone via admin console | 55 mins | 12/17/00 10:05 PM | 12/17/00 11:00 PM | 48 | Mike L |
| 50 | Validate service component disablement | 0 days | 12/17/00 10:05 PM | 12/17/00 10:05 PM | 48 | Mike B |
| 51 | Disable cron jobs, foglight alerts | 15 mins | 12/17/00 10:05 PM | 12/17/00 10:20 PM | 50 | Mike L |
| 52 | Site is taken down - redirected to outage page | 0 days | 12/17/00 11:00 PM | 12/17/00 11:00 PM | Mike L | |
| 53 | Validate outage notice | 0 days | 12/17/00 11:00 PM | 12/17/00 11:00 PM | 52 | Mike B |
| 54 | Application servers are shutdown | 3 mins | 12/17/00 11:00 PM | 12/17/00 11:03 PM | 53 | Mike L |
| 55 | Verify DB connections are shutdown | 1 min | 12/17/00 11:03 PM | 12/17/00 11:04 PM | 54 | Vishal |
| 56 | Switch logs on db1 | 3 mins | 12/17/00 11:04 PM | 12/17/00 11:07 PM | 55 | Vishal |
| 57 | Run snapshots | 30 mins | 12/17/00 11:07 PM | 12/17/00 11:37 PM | 56 | Vishal |
| 58 | Move logs on to db2 | 5 mins | 12/17/00 11:37 PM | 12/17/00 11:42 PM | 57 | Ramesh |
| 59 | Change dynamo symlinks | 3 mins | 12/17/00 11:03 PM | 12/17/00 11:06 PM | 54 | Mike L |
| 60 | Run makeCorpSite script for http1-6 and as1-5 | 3 mins | 12/17/00 11:06 PM | 12/17/00 11:09 PM | 59 | Mike L |
| 61 | Untar MEP tar ball | 2 mins | 12/17/00 11:09 PM | 12/17/00 11:11 PM | 60 | Keith |
| 62 | Wait for logs to apply to db2 (sync with db1) | 5 mins | 12/17/00 11:42 PM | 12/17/00 11:47 PM | 58 | Ramesh |
| 63 | Drop snapshot logs | 15 mins | 12/17/00 11:47 PM | 12/18/00 12:02 AM | 62 | Vishal |
| 64 | Shutdown standby instance and listener on db2 | 2 mins | 12/17/00 11:47 PM | 12/17/00 11:49 PM | 62 | Ramesh |
| 65 | Shutdown PROD instance and listener on db1 | 2 mins | 12/18/00 12:02 AM | 12/18/00 12:04 AM | 63 | Vishal |
| 66 | Startup PROD instance and listener on db1 | 2 mins | 12/18/00 12:04 AM | 12/18/00 12:06 AM | 65 | Vishal |
| 67 | Run DataNorm migration scripts | 0.08 days | 12/18/00 12:06 AM | 12/18/00 12:44 AM | ||
| 68 | Address Group | 15 mins | 12/18/00 12:06 AM | 12/18/00 12:21 AM | 66 | Vishal |
| 69 | Login | 3 mins | 12/18/00 12:21 AM | 12/18/00 12:24 AM | 68 | Vishal |
| 70 | Consumer 2.0 | 4 mins | 12/18/00 12:24 AM | 12/18/00 12:28 AM | 69 | Vishal |
| 71 | Patch (Login optimization) | 2 mins | 12/18/00 12:28 AM | 12/18/00 12:30 AM | 70 | |
| 72 | International Shipping | 10 mins | 12/18/00 12:30 AM | 12/18/00 12:40 AM | 71 | Vishal |
| 73 | Migration | 2 mins | 12/18/00 12:40 AM | 12/18/00 12:42 AM | 72 | Vishal |
| 74 | Run Audit scripts | 2 mins | 12/18/00 12:42 AM | 12/18/00 12:44 AM | 73 | Ramesh |
| 75 | Run Catalog Lite migration scripts | 16 mins | 12/18/00 12:44 AM | 12/18/00 1:00 AM | 74 | Vishal |
| 76 | Run Audit scripts | 2 mins | 12/18/00 1:00 AM | 12/18/00 1:02 AM | 75 | Ramesh |
| 77 | Run CSP migration scripts | 3 mins | 12/18/00 1:02 AM | 12/18/00 1:05 AM | 76 | Vishal |
| 78 | Run Audit scripts | 2 mins | 12/18/00 1:05 AM | 12/18/00 1:07 AM | 77 | Ramesh |
| 79 | Run small projects migration scripts | 1 min | 12/18/00 1:07 AM | 12/18/00 1:08 AM | 78 | Vishal |
| 80 | Run Audit scripts | 2 mins | 12/18/00 1:08 AM | 12/18/00 1:10 AM | 79 | Ramesh |
| 81 | Run WATR migration scripts | 17 mins | 12/18/00 1:10 AM | 12/18/00 1:27 AM | 80 | Vishal |
| 82 | Run Audit scripts | 2 mins | 12/18/00 1:27 AM | 12/18/00 1:29 AM | 81 | Ramesh |
| 83 | Run updated PL/SQL package scripts | 6 mins | 12/18/00 1:29 AM | 12/18/00 1:35 AM | 82 | Vishal |
| 84 | Import Resource tables to tsp@prod (validate row counts) | 15 mins | 12/18/00 1:35 AM | 12/18/00 1:50 AM | 83 | Vishal |
| 85 | Import Skinner tables to tsp@prod (validate row counts) | 15 mins | 12/18/00 1:50 AM | 12/18/00 2:05 AM | 84 | Vishal |
| 86 | Run Audit scripts | 2 mins | 12/18/00 2:05 AM | 12/18/00 2:07 AM | 85 | Ramesh |
| 87 | Create snapshot logs (before site goes live) | 15 mins | 12/18/00 2:07 AM | 12/18/00 2:22 AM | 86 | Vishal |
| 88 | Shutdown and restart PROD instance and listener | 4 mins | 12/18/00 2:22 AM | 12/18/00 2:26 AM | 87 | Vishal |
| 89 | DBA QA time for reviewing contstraints | 10 mins | 12/18/00 2:26 AM | 12/18/00 2:36 AM | 88 | Vishal,Ramesh |
| 90 | Add dnsCheck cron job | 15 mins | 12/17/00 11:09 PM | 12/17/00 11:24 PM | 60 | Mike L |
| 91 | Reconfigure as1 to point to http3.bigstep.com instead of www.bigstep.com | 5 mins | 12/18/00 2:07 AM | 12/18/00 2:12 AM | 86 | Mike L |
| 92 | Validate base functions | 40 mins | 12/18/00 2:12 AM | 12/18/00 2:52 AM | 91 | Mike B |
| 93 | Reconfigure as1 to point to www.bigstep.com instead of http3.bigstep.com | 5 mins | 12/18/00 2:52 AM | 12/18/00 2:57 AM | 92 | Mike L |
| 94 | Start all app servers | 5 mins | 12/18/00 2:57 AM | 12/18/00 3:02 AM | 93 | Mike L |
| 95 | Start migrations via admin console | 5 mins | 12/18/00 3:02 AM | 12/18/00 3:07 AM | 94 | Mike L |
| 96 | Monitor status of migrations for failure rates | 60 mins | 12/18/00 3:07 AM | 12/18/00 4:07 AM | 95 | Kirt |
| 97 | Bring up entire service | 1 min | 12/18/00 4:07 AM | 12/18/00 4:08 AM | 96 | Mike L |
| 98 | Re-enable cron jobs, foglight alerts | 5 mins | 12/18/00 4:08 AM | 12/18/00 4:13 AM | 97 | Mike L |
| 99 | Kickoff load_reporting.sh on bfs1 | 1 min | 12/18/00 4:13 AM | 12/18/00 4:14 AM | 98 | Mike L |
| 100 | Kickoff sustained load test against production | 90 mins | 12/18/00 4:14 AM | 12/18/00 5:44 AM | 99 | Mike B |
| 101 | Send email to notify customers that the service is back online | 5 mins | 12/18/00 5:44 AM | 12/18/00 5:49 AM | 100 | Mike L |
| 102 | Monitor system performance | 1 hr | 12/18/00 5:49 AM | 12/18/00 6:49 AM | 101 | Mike L,Matt |
| 103 | Re-enable cron job on db2 for standby | 1 min | 12/18/00 10:49 AM | 12/18/00 10:50 AM | 102FS+0.5 days | Ramesh |
| 104 | ||||||
| 105 | Post-rollout support staff | 46.87 days? | 12/3/00 12:01 AM | 12/18/00 3:00 PM | ||
| 106 | On-site | 1.06 days | 12/18/00 6:30 AM | 12/18/00 3:00 PM | ||
| 107 | Sys Admin | 8 hrs | 12/18/00 6:30 AM | 12/18/00 2:30 PM | 102 | Seth |
| 108 | DBA | 8 hrs | 12/18/00 6:30 AM | 12/18/00 2:30 PM | 102 | Mahender |
| 109 | Engineers | 8 hrs | 12/18/00 7:00 AM | 12/18/00 3:00 PM | 102 | |
| 110 | Off-site | 1 day? | 12/3/00 12:01 AM | 12/3/00 8:01 AM |